IPMAT Indore 2023
Arithmetic
Time & Work
Medium
Amisha can complete a particular task in twenty days. After working for four days she fell sick for four days and resumed the work on the ninth day but with half of her original work rate. She completed the task in another twelve days with the help of a co-worker who joined her from the ninth day. The number of days required for the co-worker to complete the task alone would be
Amisha can complete a particular task in twenty days. After working for four days she fell sick for four days and resumed the work on the ninth day but with half of her original work rate. She completed the task in another twelve days with the help of a co-worker who joined her from the ninth day. The number of days required for the co-worker to complete the task alone would be
Entered answer:
Correct Answer: 24