IPMAT Rohtak 2019
Arithmetic
Time & Work
Medium
Work done by P in one day is double the work done by Q in one day and work done by Q in one day is thrice the work done by R in one day. If P, Q, and R together can complete the work in 30 days, then in how many days P alone can do the work?
Work done by P in one day is double the work done by Q in one day and work done by Q in one day is thrice the work done by R in one day. If P, Q, and R together can complete the work in 30 days, then in how many days P alone can do the work?
Correct Option: 4
Let P's work per day = units Then Q's work per day = units And R's work per day = unitsTotal work per day by all three = units per dayIf total work = unit and time taken = days Therefore, P can do unit work per daySo P alone will take days to complete the work.